Canada - China BIT (2012)
Previous page Next page

3. Nothing in this Agreement shall be construed to require a Contracting Party to furnish or allow access to information the disclosure of which would be contrary to the Contracting Party's law protecting information concerning the taxation affairs of a taxpayer.

4. The provisions of Article 10 shall apply to taxation measures.

5. No claim may be made by an investor pursuant to paragraph 4 unless:

(a) the investor provides a copy of the notice of claim to the taxation authorities of the Contracting Parties; and

(b) six months after receiving notification of the claim by the investor, the taxation authorities of the Contracting Parties fail to reach a joint determination that the measure in question is not an expropriation.

6. The taxation authorities referred to in this Article shall be the following until otherwise notified by a Contracting Party:

(a) for Canada: the Assistant Deputy Minister, Tax Policy, of the Department of Finance Canada;

(b) for China: the Ministry of Finance and State Administration of Taxation or an authorized representative of the Ministry of Finance and State Administration of Taxation.

7. The Contracting Parties shall notify each other promptly by diplomatic note of the successors to the tax authorities identified in sub-paragraphs 6(a) and (b).

Article 15. Disputes between the Contracting Parties

1. Any dispute between the Contracting Parties concerning the interpretation or application of this Agreement shall, as far as possible, be settled by consultation through diplomatic channels.

2. If a dispute cannot thus be settled within six months, it shall, upon the request of either Contracting Party, be submitted to an ad hoc arbitral tribunal.

3. Such tribunal shall be comprised of three arbitrators. Within two months from the date on which either Contracting Party receives the written notice requesting arbitration from the other Contracting Party, each Contracting Party shall appoint one arbitrator. Those two arbitrators shall jointly select a third arbitrator, who shall be a national of a third State which has diplomatic relations with both Contracting Parties. The third arbitrator shall be appointed by the two Contracting Parties as Chairman of the arbitral tribunal within two months from the date of appointment of the other two arbitrators.

4. If within the periods specified in paragraph 3 of this Article the necessary appointments have not been made, either Contracting Party may, in the absence of any other agreement, invite the President of the International Court of Justice to appoint any arbitrator who has or have not yet been appointed. If the President is a national of either Contracting Party or is otherwise prevented from discharging this function, the next most senior member of the International Court of Justice who is not a national of either Contracting Party shall be invited to make the necessary appointments.

5. The arbitral tribunal shall determine its own procedure.

6. The arbitral tribunal shall reach its decision by a majority of votes. The arbitral tribunal shall, upon the request of either Contracting Party, explain the reasons for its decision. Unless otherwise agreed, the arbitral tribunal shall make best efforts to render its decision within six months of the appointment of the Chairman in accordance with paragraphs 3 and 4 of this Article.

7. Each Contracting Party shall bear the cost of its appointed arbitrator and of its representation in the arbitral proceedings. The relevant costs of the Chairman and the arbitral tribunal shall be borne in equal parts by the Contracting Parties.

8. The decision of the arbitral tribunal shall be final and binding on both Contracting Parties. The Contracting Parties shall, if necessary, within 60 days of the decision of an arbitral tribunal, meet and decide on the manner in which to resolve their dispute. That decision shall normally

Implement the decision of the arbitral tribunal. If the Contracting Parties fail to reach a decision, the Contracting Party bringing the dispute shall be entitled to receive compensation of equivalent value to the arbitral tribunal's award.

Article 16. Denial of Benefits

1. A Contracting Party may, at any time including after the institution of arbitration proceedings in accordance with Part C, deny the benefits of this Agreement to an investor of the other Contracting Party that is an enterprise of that other Contracting Party and to covered investments of that investor:

(a) if investors of a non-Contracting Party own or control the enterprise; and

(b) the denying Contracting Party adopts or maintains measures with respect to the non-Contracting Party:

(i) that prohibit transactions with the enterprise; or

(ii) that would be violated or circumvented if the benefits of this Agreement were accorded to the enterprise or to its covered investments.

2. A Contracting Party may, at any time including after the institution of arbitration proceedings in accordance with Part C, deny the benefits of this Agreement to an investor of the other Contracting Party that is an enterprise of that other Contracting Party and to covered investments of that investor if investors of a non-Contracting Party or of the denying Contracting Party own or control the enterprise and the enterprise has no substantial business activities in the territory of the other Contracting Party under whose law it is constituted or organized.

3. For greater certainty, a Contracting Party may deny the benefits of this Agreement pursuant to paragraphs 1 and 2 at any time, including after the initiation of arbitration proceedings in accordance with Part C.

Article 17. Transparency of Laws, Regulations and Policies

1. Each Contracting Party shall, with a view to promoting the understanding of its laws and policies that pertain to or affect a covered investment:

(a) make such laws and policies public and readily accessible;

(b) if requested, provide copies of specified laws and policies to the other Contracting Party; and

(c) if requested, consult with the other Contracting Party with a view to explaining specified laws and policies.

2. Each Contracting Party shall ensure that its laws, regulations and policies pertaining to the conditions of admission of investments, including procedures for application and registration, criteria used for assessment and approval, timelines for processing an application and rendering a decision, and review or appeal procedures of a decision, are administered in a manner that enables investors of the other Contracting Party to become acquainted with them.

3. Each Contracting Party is encouraged to:

(a) publish in advance any measure that it proposes to adopt; and

(b) Provide interested persons and the other Contracting Party a reasonable opportunity to comment on the proposed measure.

Article 18. Consultations

1. The representatives of the Contracting Parties may hold meetings for the purpose of:

(a) reviewing the implementation of this Agreement;

(b) reviewing the interpretation or application of this Agreement;

(c) exchanging legal information;

(d) addressing disputes arising out of investments

(e) studying other issues in connection with the facilitation or encouragement of investment, including measures referred to in paragraph 3.

2. Further to consultations under this Article, the Contracting Parties may take any action as they may jointly decide, including making and adopting rules supplementing the applicable arbitral rules under Part C of this Agreement and issuing binding interpretations of this Agreement.

3. The Contracting Parties recognize that it is inappropriate to encourage investment by waiving, relaxing, or otherwise derogating from domestic health, safety or environmental measures.

Part C.

Article 19. Purpose

Without prejudice to the rights and obligations of the Contracting Parties under Article 15, this Part establishes a mechanism for the settlement of investment disputes.

Article 20. Claim by an Investor of a Contracting Party

1. An investor of a Contracting Party may submit to arbitration under this

Part a claim that the other Contracting Party has breached an obligation: o (a) under Articles 2 to 7(2), 9, 10 to 13, 14(4) or 16, if the breach is with respect to investors or covered investments of investors to which sub-paragraph (b) does not apply, or o (b) under Article 10 or 12 if the breach is with respect to investors of a Contracting Party in financial institutions in the other Contracting Party's territory or covered investments of such investors in financial institutions in the other Contracting Party's territory,

And that the investor or a covered investment of the investor has incurred loss or damage by reason of, or arising out of, that breach.

(a) Where an investor submits a claim to arbitration under this Article,

And the disputing Contracting Party invokes Article 33(3), the investor-State tribunal established pursuant to this Part may not decide whether and to what extent Article 33(3) is a valid defence to the claim of the investor. It shall seek a report in writing from the Contracting Parties on this issue. The investor-State tribunal may not proceed pending receipt of such a report or of a decision of a State-State arbitral tribunal, should such a State-State arbitral tribunal be established.

(b) Pursuant to a request for a report received in accordance with subparagraph (a), the financial services authorities of the Contracting Parties shall engage in consultations. If the financial services authorities of the Contracting Parties reach a joint decision on the issue of whether and to what extent Article 33(3) is a valid defence to the claim of the investor, they shall prepare a written report describing their joint decision. The report shall be transmitted to the investor-State tribunal, and shall be binding on the investor-State tribunal.

(c) If, after 60 days, the financial services authorities of the Contracting Parties are unable to reach a joint decision on the issue of whether and to what extent Article 33(3) is a valid defence to the claim of the investor, the issue shall, within 30 days, be referred by either of the Contracting Parties to a State-State arbitral tribunal established pursuant to Article 15. In such a case, the provisions requiring consultations between the Contracting Parties in Article 15(1) and (2) shall not apply. The decision of the State-State arbitral tribunal shall be transmitted to the investor-State tribunal, and shall be binding on the investor-State tribunal. All of the members of any such State-State arbitral tribunal shall have expertise or experience in financial services law or practice, which may include the regulation of financial institutions.

Article 21. Conditions Precedent to Submission of a Claim to Arbitration

1. Before a disputing investor may submit a claim to arbitration, the disputing parties shall first hold consultations in an attempt to settle a claim amicably. Consultations shall be held within 30 days of the submission of the notice of intent to submit a claim to arbitration, unless the disputing parties otherwise agree. The place of consultation shall be the capital of the disputing Contracting Party, unless the disputing parties otherwise agree.

2. Subject to the Party-specific requirements set out in Annex C.21, a disputing investor may submit a claim to arbitration under Article 20 only if:

(a) the investor consents to arbitration in accordance with the procedures set out in this Agreement and delivers notice of such consent to the disputing Contracting Party together with the submission of a claim to arbitration;

(b) at least six months have elapsed since the events giving rise to the claim;

(c) the investor has delivered to the disputing Contracting Party written notice of its intent to submit a claim to arbitration at least four months prior to submitting the claim;

(d) the investor has delivered, with its notice of intent to submit a claim to arbitration under sub-paragraph (c), evidence establishing that it is an investor of the other Contracting Party;

(e) the investor has waived its right to initiate or continue dispute settlement proceedings under any agreement between a third State and the disputing Contracting Party in relation to the measure alleged to be a breach of an obligation under Part B of this Agreement; and

(f) not more than three years have elapsed from the date on which the investor first acquired, or should have first acquired, knowledge of the alleged breach and knowledge that the investor or a covered investment of the investor has incurred loss or damage thereby.

Article 22. Submission of a Claim to Arbitration

1. A disputing investor who meets the conditions precedent provided for in Article 21 may submit the claim to arbitration under:

(a) the ICSID Convention, provided that both Contracting Parties are parties to that Convention;

(b) the Additional Facility Rules of ICSID, provided that one Contracting Party, but not both, is a party to the ICSID Convention; or

(c) the UNCITRAL Arbitration Rules,

As supplemented or modified by the rules set out in this Agreement or adopted by the Contracting Parties.

2. A claim is submitted to arbitration under this Part when:

(a) the request for arbitration under Article 36(1) of the ICSID Convention is received by the Secretary General;

(b) the notice of arbitration under Article 2 of Schedule C of the ICSID Additional Facility Rules is received by the Secretary General; or

(c) the notice of arbitration given under the UNCITRAL Arbitration Rules is received by the disputing Contracting Party.

3. Delivery of notice and other documents to a Contracting Party shall be made to the place named for that Contracting Party below:

(a) For Canada: Office of the Deputy Attorney General of Canada, Justice Building, 239 Wellington Street, Ottawa, Ontario, K1A 0H8;

(b) For China: Department of Treaty and Law, Ministry of Commerce of the People's Republic of China.

4. The Contracting Parties shall notify each other promptly by diplomatic note of any change in the place for delivery.

Article 23. Consent to Arbitration

Each Contracting Party consents to the submission of a claim to arbitration in accordance with the procedures set out in this Agreement. Failure to meet any of the conditions precedent provided for in Article 21 shall nullify that consent.

Article 24. Arbitrators

1. Except in respect of a Tribunal established under Article 26, and unless the disputing parties agree otherwise, the Tribunal shall comprise three arbitrators, one arbitrator appointed by each of the disputing parties and the third, who shall be the presiding arbitrator, appointed by agreement of the disputing parties.

2. Arbitrators shall:

(a) have expertise or experience in public international law, international trade or international investment rules, or the resolution of disputes arising under international trade or international investment agreements;

(b) be independent of, and not be affiliated with, or take instructions from, either Contracting Party or disputing party; and

(c) Comply with any additional rules where such rules are agreed to by the Contracting Parties.

3. Where the claimant claims that a dispute involves measures adopted or maintained by the disputing Contracting Party relating to financial institutions of the other Contracting Party, or investors of the other Contracting Party and covered investments of such investors in financial institutions in the disputing Contracting Party's territory, then:

(a) where the disputing parties are in agreement, the arbitrators shall, in addition to the criteria set out in paragraph 2, have expertise or experience in financial services law or practice, which may include the regulation of financial institutions; or

(b) where the disputing parties are not in agreement,

(i) each disputing party may select arbitrators who meet the qualifications set out in subparagraph (a), and

(ii) if the disputing Contracting Party invokes Article 33(4), the presiding arbitrator shall meet the qualifications set out in subparagraph (a).

4. If the disputing parties do not agree on the remuneration of the arbitrators before the constitution of the Tribunal, the prevailing ICSID rate for arbitrators shall apply.

5. If a Tribunal, other than a Tribunal established under Article 26, has not been constituted within 90 days from the date that a claim is submitted to arbitration, the Secretary General of ICSID, on the request of either disputing party, shall appoint, in his or her discretion, the arbitrator or arbitrators not yet appointed, except that the presiding arbitrator shall not be a national of either Contracting Party.

Article 25. Agreement to Appointment of Arbitrators

For the purposes of Article 39 of the ICSID Convention and Article 7 of Schedule C to the Additional Facility Rules of ICSID, and without prejudice to an objection to an arbitrator based on a ground other than citizenship or permanent residence:

(a) the disputing Contracting Party agrees to the appointment of each individual member of a Tribunal established under the ICSID Convention or the Additional Facility Rules of ICSID;

(b) a disputing investor may submit a claim to arbitration, or continue a claim, under the ICSID Convention or the Additional Facility Rules of ICSID, only on condition that the disputing investor agrees in writing to the appointment of each individual member of the Tribunal.

Article 26. Consolidation

1. Where two or more claims have been submitted separately to arbitration under Article 20 and the claims have a question of law or fact

In common and arise out of the same events or circumstances, any disputing party may seek a consolidation order in accordance with either the agreement of all the disputing parties sought to be covered by the order, or the terms of paragraphs 2 through 9.

2. A disputing party that seeks a consolidation order under this Article shall deliver, in writing, a request to the Secretary-General of ICSID and to all the disputing parties sought to be covered by the order and shall specify in the request: the names and addresses of all the disputing parties sought to be covered by the order; the nature of the order sought; and the grounds on which the order is sought.

3. Unless the Secretary-General of ICSID finds within 30 days after receiving a request under paragraph 2 that the request is manifestly unfounded, a tribunal shall be established under this Article.

4. Unless all the disputing parties sought to be covered by the order otherwise agree, a tribunal established under this Article shall comprise three arbitrators: one arbitrator appointed by agreement of the claimants; one arbitrator appointed by the respondent; and the presiding arbitrator appointed by the Secretary-General of ICSID, provided, however, that the presiding arbitrator shall not be a national of either Contracting Party.

5. If, within 60 days after the Secretary-General of ICSID receives a request made under paragraph 2, the disputing Contracting Party fails or the claimants fail to appoint an arbitrator in accordance with paragraph 4, the Secretary-General of ICSID, at the request of any disputing party sought to be covered by the order, shall appoint the arbitrator or arbitrators not yet appointed.

6. Where a tribunal established under this Article is satisfied that two or more claims that have been submitted to arbitration under Article 20 have a question of law or fact in common, and arise out of the same events or circumstances, the tribunal may, in the interest of fair and efficient resolution of the claims, and after hearing the disputing parties, by order: assume jurisdiction over, and hear and determine together, all or part of the claims; or assume jurisdiction over, and hear and determine one or more of the claims, the determination of which it believes would assist in the resolution of the others.

7. A tribunal established under this Article shall conduct its proceedings in accordance with the UNCITRAL Arbitration Rules, except as modified by this Section.

8. A tribunal established under Articles 22 through 25 shall not have jurisdiction to decide a claim, or a part of a claim, over which a tribunal established under this Article has assumed jurisdiction.

9. On application of a disputing party, a tribunal established under this Article may, pending its decision under paragraph 6, order that the proceedings of a tribunal established under Article 22 through 25 be stayed, unless the latter tribunal has already adjourned its proceedings.

Article 27. The Non-disputing Contracting Party: Documents and Participation

1. A disputing Contracting Party shall deliver to the other Contracting Party a copy of the notice of intent to submit a claim to arbitration, and the relevant document submitted pursuant to Article 22(2) no later than 30 days after the date that such documents have been delivered to the disputing Contracting Party. The non-disputing Contracting Party shall be entitled, at its cost, to receive from the disputing Contracting Party a copy of the evidence that has been tendered to the Tribunal, copies of all pleadings filed in the arbitration, and the written argument of the disputing parties. The Contracting Party receiving such information shall treat the information as if it were a disputing Contracting Party.

2. The non-disputing Contracting Party shall have the right to attend any hearings held under this Part of this Agreement. Upon written notice to the disputing parties, the non-disputing Contracting Party may make submissions to a Tribunal on a question of interpretation of this Agreement.

Article 28. Public Access to Hearings and Documents

1. Any Tribunal award under this Part shall be publicly available, subject to the redaction of confidential information. Where a disputing Contracting Party determines that it is in the public interest to do so and notifies the Tribunal of that determination, all other documents submitted to, or issued by, the Tribunal shall also be publicly available, subject to the redaction of confidential information.

2. Where, after consulting with a disputing investor, a disputing Contracting Party determines that it is in the public interest to do so and notifies the Tribunal of that determination, hearings held under this Part shall be open to the public. To the extent necessary to ensure the protection of confidential information, including business confidential information, the Tribunal may hold portions of hearings in camera.

3. A disputing party may disclose to other persons in connection with the arbitral proceedings such unredacted documents as it considers necessary for the preparation of its case, but it shall ensure that those persons protect the confidential information in such documents.

4. The Contracting Parties may share with officials of their respective federal and sub-national governments all relevant unredacted documents in the course of dispute settlement under this Agreement, but they shall ensure that those persons protect any confidential information in such documents.

5. To the extent that a Tribunal's confidentiality order designates information as confidential and a Contracting Party's law on access to information requires public access to that information, the Contracting Party's law on access to information shall prevail. However, a Contracting Party should endeavour to apply its law on access to information so as to protect information designated confidential by the Tribunal.

Article 29. Submissions by a Non-disputing Party

A Tribunal, after consultation with the disputing parties, may accept written submissions from a person or entity that is not a disputing party if that non-disputing party has a significant interest in the arbitration. The Tribunal shall ensure that any non-disputing party submission does not disrupt the proceedings and that neither disputing party is unduly burdened or unfairly prejudiced by it.

An application to the Tribunal for leave to file a non-disputing party submission, and the filing of a submission, if allowed by the Tribunal, shall be made in accordance with Annex C.29.

Article 30. Governing Law

1. A Tribunal established under this Part shall decide the issues in dispute in accordance with this Agreement, and applicable rules of international law, and where relevant and as appropriate, take into consideration the law of the host Contracting Party. An interpretation by the Contracting Parties of a provision of this Agreement shall be binding on a Tribunal established under this Part, and any award under this Part shall be consistent with such interpretation.

2. Where a disputing Contracting Party asserts as a defence that the measure alleged to be a breach is within the scope of the reservations and exceptions set out in Article 8(1), (2) and (3), on request of the disputing Contracting Party, the Tribunal shall request the interpretation of the Contracting Parties on the issue. The Contracting Parties, within 60 days of delivery of the request, shall submit in writing their joint interpretation to the Tribunal. The interpretation shall be binding on the Tribunal. If the Contracting Parties fail to submit an interpretation within 60 days, the Tribunal shall decide the issue.

Article 31. Interim Measures of Protection and Final Award

1. A Tribunal may recommend an interim measure of protection to preserve the rights of a disputing party, or to ensure that the Tribunal's jurisdiction is made fully effective, including a recommendation to preserve evidence in the possession or control of a disputing party or to

Protect the Tribunal's jurisdiction. A Tribunal shall not recommend attachment or enjoin the application of the measure alleged to constitute a breach referred to in Article 20.

2. Where a Tribunal makes a final award against the disputing Contracting Party, the Tribunal may award, separately or in combination, and subject to the requirements in paragraph 3, only:

(a) monetary damages and any applicable interest;

(b) restitution of property, in which case the award shall provide that the disputing Contracting Party may pay monetary damages and any applicable interest in lieu of restitution.

The Tribunal may also award costs in accordance with the applicable arbitration rules.

3. Where a claim is made for damages to a covered investment that is a juridical person that the investor owns or controls:

(a) an award of monetary damages and any applicable interest shall provide that the sum be paid to that covered investment;

(b) an award of restitution of property shall provide that restitution be made to that covered investment; and

(c) the award shall provide that it is made without prejudice to any right that any person may have in the relief under applicable domestic law.

4. A Tribunal shall not order a disputing Contracting Party to pay punitive damages.

Article 32. Finality and Enforcement of an Award

1. An award made by a Tribunal shall have no binding force except between the disputing parties and in respect of that particular case.

2. Subject to paragraph 3 and the applicable review procedure for an interim award, a disputing party shall abide by and comply with an award without delay.

3. A disputing party may not seek enforcement of a final award until:

(a) in the case of a final award made under the ICSID Convention:

(i) 120 days have elapsed from the date the award was rendered, provided that a disputing party has not requested the award be revised or annulled, or

(ii) revision or annulment proceedings have been completed; and

(b) in the case of a final award under the ICSID Additional Facility Rules or the UNCITRAL Arbitration Rules:

(i) 90 days have elapsed from the date the award was rendered and no disputing party has commenced a proceeding to revise, set aside or annul the award, or

(ii) a court has dismissed or allowed an application to

Revise, set aside or annul the award and there is no further appeal.

4. Each Contracting Party shall provide for the enforcement of an award in its territory.

Part D.

Article 33. General Exceptions

  • Part   A 1
  • Article   1 Definitions 1
  • Part   B 1
  • Article   2 Scope and application 1
  • Article   3 Promotion and admission of investment 1
  • Article   4 Minimum standard of treatment 1
  • Article   5 Most-favoured-nation treatment 1
  • Article   6 National treatment 1
  • Article   7 Senior management, boards of directors and entry of personnel 1
  • Article   8 Exceptions 1
  • Article   9 Performance requirements 1
  • Article   10 Expropriation 1
  • Article   11 Compensation for losses 1
  • Article   12 Transfers 1
  • Article   13 Subrogation 1
  • Article   14 Taxation 1
  • Article   15 Disputes between the contracting parties 2
  • Article   16 Denial of benefits 2
  • Article   17 Transparency of laws, regulations and policies 2
  • Article   18 Consultations 2
  • Part   C 2
  • Article   19 Purpose 2
  • Article   20 Claim by an investor of a contracting party 2
  • Article   21 Conditions precedent to submission of a claim to arbitration 2
  • Article   22 Submission of a claim to arbitration 2
  • Article   23 Consent to arbitration 2
  • Article   24 Arbitrators 2
  • Article   25 Agreement to appointment of arbitrators 2
  • Article   26 Consolidation 2
  • Article   27 The non-disputing contracting party: documents and participation 2
  • Article   28 Public access to hearings and documents 2
  • Article   29 Submissions by a non-disputing party 2
  • Article   30 Governing law 2
  • Article   31 Interim measures of protection and final award 2
  • Article   32 Finality and enforcement of an award 2
  • Part   D 2
  • Article   33 General exceptions 3
  • Article   34 Exclusions 3
  • Article   35 Entry into force and termination 3