3. Where a claim is submitted on behalf of an enterprise of the respondent Contracting Party, the arbitral award shall be made to the enterprise.

4. In any arbitration conducted under this Section, at the request of a disputing party, a tribunal shall, before issuing a decision or award on liability, transmit its proposed decision or award to the disputing parties. Within sixty (60) days after the tribunal transmits its proposed decision or award, the disputing parties may submit written comments to the tribunal concerning any aspect of the proposed decision or award. The tribunal shall consider any such comments and issue its decision or award not later than forty-five(45) days after the expiration of the sixty (60) day comment period.

Article 17. CONSOLIDATION

1. Where two or more claims have been submitted separately to arbitration under this Section, and the claims raised have a question of law or fact in common and arise out of the same events or circumstances, any disputing party may seek a consolidation order, in accordance with the agreement of all the disputing parties sought to be covered by the order or the terms of this Article.

2. A disputing party that seeks a consolidation order under this Article shall deliver, in writing, a request to the Secretary-General ofICSID and to all the disputing parties sought to be covered by the order, specifying the name and address of all the disputing parties sought to be covered by the order; the nature of the order sought; and the grounds on which the order is sought.

3. Unless the Secretary-General of ICSID finds within thirty (30) days after receiving a request in conformity with paragraph 2 that the request is manifestly unfounded, a tribunal shall be established under this Article.

4. Unless all the disputing parties sought to be covered by the consolidation order otherwise agree, the tribunal established under this Article shall comprise three arbitrators, who shall not be nationals or permanent residents of either Contracting Party, and who shall be appointed as follows:

(a) one arbitrator appointed by agreement of the disputing investors;

(b) one arbitrator appointed by the respondent Contracting Party; and

(c) the chairman of the arbitral tribunal appointed by the Secretary-General of ICSID.

5. If, within the sixty (60) days after the Secretary-General of ICSID receives a request made under paragraph 2, the respondent Contracting Party fails or the disputing investors fail to appoint an arbitrator in accordance with paragraph 4, the Secretary-General of ICSID, on request of any disputing party sought to be covered by the order, shall appoint the arbitrator or arbitrators not yet appointed.

6. Where a tribunal established under this Article is satisfied that two or more claims that have been submitted to arbitration in accordance with Article 11 (Institution of Arbitral Proceedings), have a question of law or fact in common, and arise out of the same events or circumstances, the tribunal may, in the interest of fair and efficient resolution of the claims, and after hearing the disputing parties, by order:

(a) assume jurisdiction over, and hear and determine together, all or part of the claims;

(b) assume jurisdiction over, and hear and determine one or more claims, whose determination it considers would assist in the resolution of the other claims; or

(c) instruct a tribunal previously established under Article 12 (Constitution of the Arbitral Tribunal) to assume jurisdiction over and to hear and determine together, all or part of the claims, provided that:

(i) that tribunal, at the request of any disputing investor, not previously a disputing party before that tribunal, shall be reconstituted with its original members, except that the arbitrator for the disputing investors shall be appointed pursuant to paragraphs 4(a) and 5; and

(ii) that tribunal shall decide whether any previous hearing must be repeated.

7. Where a tribunal has been established under this Article, a disputing investor that has submitted a claim to arbitration pursuant to Article 11 (Institution of Arbitral Proceedings) and that has not been named in a request made under paragraph 2, may make a written request to the tribunal that it be included in any order issued under paragraph 6, specifying:

(a) the name and address of the disputing investor;

(b) the nature of the order sought; and

(c) the grounds on which the order is sought. 

The claimant shall provide the Secretary-General ofICSID with a copy of his request.

8. A tribunal established pursuant to this Article shall conduct the proceedings m accordance with the UNCITRAL Arbitration Rules, except as modified by this Section.

9. A tribunal established under Article 12 (Constitution of the Arbitral Tribunal) shall not have jurisdiction to decide a claim or a part of a claim over which a tribunal established or instructed under this Article has assumed jurisdiction.

10. On application of a disputing party, a tribunal established pursuant to this Article may, pending its decision under paragraph 6, order that the proceedings of a tribunal established under Article 12 (Constitution of the Arbitral Tribunal) be stayed, unless the latter tribunal has already adjourned its proceedings. 

Section TWO. SETTLEMENT OF DISPUTES BETWEEN THE CONTRACTING PARTIES

Article 18. SCOPE

1. This Section applies to the settlement of disputes between the Contracting Parties arising from the interpretation or application of the provisions of this Agreement.

2. This Section shall not apply to any dispute concerning any measure adopted or maintained or any treatment accorded to investors or investments by a Contracting Party in respect of tobacco or tobacco-related products (2) that is aimed at protecting or promoting human health.

(2) For the purpose of this Agreement, "tobacco products" means products under Harmonised System Chapter 24 (Tobacco and Manufactured Tobacco Substitutes) and tobacco-related products falling outside Harmonised System Chapter 24 (Tobacco and Manufactured Tobacco Substitutes).

Article 19. CONSULTATIONS AND NEGOTIATIONS

1. Either Contracting Party may request in writing, consultations on the interpretation or application of this Agreement. If a dispute arises between the Contracting Parties on the interpretation or application of this Agreement, it shall, to the extent possible, be settled amicably through consultations and negotiation.

2. In the event the dispute is not settled through the means mentioned above within twelve (12) months from the date such negotiations or consultations were requested in writing, then, unless the Contracting Parties agree otherwise, either Contracting Party may submit such dispute to an arbitral tribunal established in accordance with this Section or, by agreement of the Contracting Parties, to any other international tribunal.

Article 20. CONSTITUTION OF THE ARBITRAL TRIBUNAL

1. Arbitration proceedings shall initiate upon written notice delivered by one Contracting Party (hereinafter referred to as "requesting Party") to the other Contracting Party (hereinafter referred to as "respondent Party") through diplomatic channels. Such notice shall contain a statement setting forth the provisions of Chapter II alleged to have been breached, the legal and factual grounds of the claim, a summary of the development and results of the consultations and negotiations pursuant to Article 19 (Consultations and Negotiations), the requesting Party's intention to initiate proceedings under this Section and the name of the arbitrator appointed by such requesting Party.

2. Within thirty (30) days after delivery of such notice, the respondent Party shall notify the requesting Party the name of its appointed arbitrator.

Article 22. THE ARBITRAL PROCEEDINGS

1. An arbitral tribunal established under this Section shall decide all questions relating to its competence and, subject to any agreement between the Contracting Parties, determine its own procedure. At any stage of the proceedings, the arbitral tribunal may propose to the Contracting Parties that the dispute be settled amicably. At all times, the arbitral tribunal shall afford a fair hearing to the Contracting Parties.

2. The arbitral tribunal shall decide the issues in dispute in accordance with this Agreement and the applicable rules and principles of international law.

3. The arbitral tribunal shall reach its decision by majority vote. The award shall be issued in writing and shall contain the applicable factual and legal findings. A signed award shall be delivered to each Contracting Party. The award shall be final and binding on the Contracting Parties. 

Chapter IV. FINAL PROVISIONS

Article 23. DENIAL OF BENEFITS

Subject to prior notification e1d consultation, a Contracting Party (the "denying Party") may deny the benefits of this Agreement to an investor of the other Contracting Party that is an enterprise of that other Contracting Party and to investments of such an investor where the denying Party establishes that the enterprise is owned or controlled by persons of a nonContracting Party, or of the denying Party, and has no substantive business operations in the territory of the other Contracting Party.

Article 24. TRANSPARENCY

1. Each Contracting Party shall ensure that its laws, regulations and administrative rulings of general application pertaining to or affecting any matter covered by this Agreement are promptly published or otherwise made available in such a manner as to enable interested persons or the other Contracting Party to become acquainted with them.

2. To the extent possible, each Contracting Party shall make the measures and international agreements of the kind referred to in paragraph 1 easily accessible, including by making such information available on the internet. Each Contracting Party shall, upon request by the other Contracting Party, promptly respond to specific questions from and provide information to the other Contracting Party with respect to matters referred to in paragraph 1.

Article 25. INFORMATION REQUIREMENTS AND DISCLOSURE OF INFORMATION

1. Notwithstanding Article 4 (Most-Favoured-Nation Treatment), a Contracting Party may require an investor of the other Contracting Party, or its investment, to provide information concerning that investment solely for informational or statistical purposes. The Contracting Party shall protect such business information that is confidential from any disclosure that would prejudice the competitive position of the investor or its investment. Nothing in this paragraph shall be construed to prevent a Contracting Party from otherwise obtaining or disclosing information in connection with the equitable and good faith application of its law.

2. Nothing in this Agreement shall require either Contracting Party to provide confidential information the disclosure of which would impede law enforcement, or otherwise be contrary to the public interest, or which would prejudice the legitimate commercial interests of particular enterprises, public or private.

Article 26. EXCEPTIONS

1. Subject to the requirement that such measures are not applied in a manner which would constitute a means of arbitrary or unjustifiable discrimination against the other Contracting Party or its investors where like conditions prevail, or a disguised restriction on investments of investors of the other Contracting Party in the territory of a Contracting Party, nothing in this Agreement shall be construed to prevent the adoption or enforcement by a Contracting Party of measures (3):

(a) necessary to protect public morals or to maintain public order (4);

(b) necessary to protect human, animal or plant life or health;

(c) necessary to secure compliance with laws or regulations which are not inconsistent with the provisions of this Agreement including those relating to:

(i) the prevention of deceptive and fraudulent practices or to deal with the effects of a default on a contract;

(ii) the protection of the privacy of individuals in relation to the processing and dissemination of personal data and the protection of confidentiality of individual records and accounts; or

(iii) safety;

(d) imposed for the protection of national treasures of artistic, historic or archaeological value; or

(e) relating to the conservation of exhaustible natural resources if such measures are made effective in conjunction with restrictions on domestic production or consumption.

2. Nothing in this Agreement shall be construed to:

(a) require a Contracting Party to furnish any information, the disclosure of which it considers contrary to its essential security interests; or

(b) preclude a Contracting Party from applying measures that it considers necessary for the fulfilment of its obligations with respect to the maintenance or restoration of international peace or security, or the protection of its own essential security interests.

(3) For greater certainty, the application of these exceptions to this Agreement shall not be interpreted so as to diminish the ability of governments to take measures where investors are not in like circumstances due to the existence of legitimate regulatory objectives.
(4) The public order exception may be invoked only where a genuine and sufficiently serious threat is posed to one of the fundamental interests of society.

Article 27. TAXATION

1. Nothing in this Agreement shall apply to taxation matters which shall, except as provided for in this Article, be governed by the domestic laws of each Contracting Party and/or any tax treaty between both Contracting Parties.

2. Article 5 (Expropriation) and Chapter III Section One (Settlement of Disputes between a Contracting Party and an Investor of the other Contracting Party) shall apply to taxation measures to the extent that such taxation measures constitute expropriation as provided for therein (5). An investor that seeks to invoke Article 5 (Expropriation) with respect to a taxation measure must first refer to the competent taxation authorities as described in paragraph 2, at the time that it gives notice under Chapter III Section One (Settlement of Disputes between a Contracting Party and an Investor of the other Contracting Party), the issue of whether that taxation measure involves an expropriation. If, within a period of six (6) months of such referral, both authorities reach an agreement that the taxation measure in question is not an expropriation, the investor shall not submit its claim to arbitration under Chapter III Section One (Settlement of Disputes between a Contracting Party and an Investor of the other Contracting Party).

3. For the purposes of this Article, "competent taxation authorities" means:

(a) in the case of Kenya, the Cabinet Secretary responsible for finance or his authorised representative; and

(b) in the case of Singapore, the Ministry of Finance, or their successors.

(5) With reference to Article 5 (Expropriation), in assessing whether a taxation measure constitutes expropriation, the following considerations are relevant: (i) the imposition of taxes does not generally constitute expropriation. The mere introduction of new taxation measures or the imposition of taxes in more than one jurisdiction in respect of an investment, does not in and of itself constitute expropriation; (ii) taxation measures which are consistent with internationally recognised tax policies, principles and practices do not constitute expropriation. In particular, taxation measures aimed at preventing the avoidance or evasion of taxes should not, generally, be considered to be expropriatory; and (iii) taxation measures which are applied on a non-discriminatory basis, as opposed to being targeted at investors of a particular nationality or specific individual taxpayers, are less likely to constitute expropriation. A taxation measure should not constitute expropriation if, when the investment is made, it was already in force, and information about the measure was made public or otherwise made publicly available.

Article 28. ENTRY INTO FORCE, DURATION AND TERMINATION

1. The Contracting Parties shall notify each other of the fulfillment of their respective internal legal procedures required for the bringing into force of this Agreement. This Agreement shall enter into force on the thirtieth day from the later of the notifications. It shall remain in force for a period of ten (10) years after its entry into force and shall continue in force unless terminated as provided for in paragraph 2.

2. A Contracting Party may, by giving one (1) year's advance notice in writing to the other Contracting Party, terminate this Agreement at the end of the initial ten (10) year period or at any time thereafter. The notice of termination shall become effective one (I) year after it has been received by the other Contracting Party.

3. The Agreement may be amended by mutual consent of the Contracting Parties in writing. The amendments shall enter into force in accordance with the same legal procedure prescribed under paragraph 1.

4. In respect of investments made prior to the date when the notice of termination of this Agreement becomes effective, the provisions of this Agreement shall remain in force for a further period of ten (10) years from that date.

Conclusion

DONE in Nairobi, on 12 June, 2018.

FOR THE GOVERNMENT OF THE REPUBLIC OF SINGAPORE

KOH POH KOON

SENIOR MINISTER OF STATE FOR TRADE AND INDUSTRY

FOR THE GOVERNMENT OF THE REPUBLIC OF KENYA

HENRY ROTICH

CABINET SECRETARY FOR THE NATIONAL TREASURY AND PLANNING

Attachments

ANNEX I. EXPROPRIATION

The Contracting Parties confirm their shared understanding that:

1. An action or a series of actions by a Contracting Party cannot constitute an expropriation unless it interferes with a tangible or intangible property right or property interest in an investment.

2. Paragraph I of Article 5 (Expropriation) addresses two situations. The first is direct expropriation, where an investment is nationalised or otherwise directly expropriated through formal transfer of title or outright seizure.

3. The second situation addressed by paragraph 1 of Article 5 (Expropriation) is indirect expropriation, where an action or series of actions by a Contracting Party has an effect equivalent to direct expropriation without formal transfer of title or outright seizure.

(a) The determination of whether an action or series of actions by a Contracting Party, in a specific fact situation, constitutes an indirect expropriation, requires a case-by-case, fact-based inquiry that considers, among other factors:

(i) the economic impact of the government action, although the fact that an action or series of actions by a Contracting Party has an adverse effect on the economic value of an investment, standing alone, does not establish that an indirect expropriation has occurred;

(ii) the extent to which the government action interferes with distinct, reasonable investment-backed expectations; and

(iii) the character of the government action.

(b) Except in rare circumstances, non-discriminatory regulatory actions by a Contracting Party that are designed and applied to protect legitimate public welfare objectives, such as public health, safety and the environment, do not constitute indirect expropriations.