9. A tribunal established under this Article, after hearing the disputing parties, may determine:
(a) Assume jurisdiction over, and hear and determine together, all or part of the claims;
(b) Assume jurisdiction over, and hear and determine one or more of the claims, provided that in doing so it would contribute to the settlement of the other claims.
10. A tribunal established under Article 13 shall lack jurisdiction to hear and determine a claim, or a part thereof, over which a consolidation tribunal has assumed jurisdiction.Article 13 shall lack jurisdiction to hear and determine a claim, or a part thereof, over which a consolidation tribunal has assumed jurisdiction.
Article 17. Place of Arbitration
Upon request of any disputing party, any arbitration under this Section shall be held in a State that is party to the New York Convention. Only for the purposes of Article 1 of the New York Convention, claims submitted to arbitration under this Section shall be considered to have arisen out of a commercial relationship or transaction.
Article 18. Indemnification
In an arbitration under this Section, a disputing Contracting Party shall not assert as a defense, counterclaim, right of setoff or otherwise, that the disputing investor has received or will receive, pursuant to an insurance or guarantee contract, indemnification or other compensation for all or part of its alleged damages.
Article 19. Applicable Law
1. A tribunal established in accordance with this Section shall decide the submitted issues in dispute in accordance with this Agreement and the applicable rules and principles of international law.
2. An interpretation jointly formulated and agreed upon by the Contracting Parties with regard to any provision of this Agreement shall be binding on any tribunal established thereunder.
Article 20. Awards and Enforcement of Awards
1. Unless the disputing parties agree otherwise, an award which provides that a Contracting Party has breached its obligations pursuant to this Agreement may only award, separately or in combination:
(a) Monetary damages and any applicable interest; or
(b) Restitution in kind, provided that the Contracting Party may pay pecuniary compensation in lieu thereof.
2. When a claim is submitted to arbitration on behalf of an enterprise:
(a) An award of restitution in kind shall provide that restitution be made to the enterprise;
(b) An award of monetary damages and any applicable interest shall provide that the total amount be paid to the enterprise; and
(c) The award shall provide that it is made without prejudice to any right that any person has or may have, with respect to the remedy granted, under applicable domestic law.
3. Arbitral awards shall be final and binding solely between the disputing parties and with respect to the particular case.
4. The arbitral award shall be public, unless the disputing parties agree otherwise.
5. A tribunal may not award punitive damages.
6. Each Contracting Party shall, within its territory, adopt all necessary measures for the effective enforcement of awards issued pursuant to this Article, and shall facilitate the enforcement of any award rendered within a proceeding in which it is a party.
7. A disputing investor may seek enforcement of an arbitral award under the ICSID Convention or the New York Convention if both Contracting Parties are parties to such treaties.ICSID Convention or the New York Convention if both Contracting Parties are parties to such treaties.
8. A disputing party may not seek enforcement of a final award until:
(a) In the case of a final award rendered under the ICSID Convention:
(i) 120 days have elapsed from the date in which the award was rendered and no disputing party has requested revision or annulment of the award; or
(ii) Revision or annulment proceedings have been completed; and
(b) In the case of a final award under the ICSID Additional Facility Rules, the UNCITRAL Arbitration Rules or any other arbitration rules selected by the disputing parties:ICSID Additional Facility Rules, the UNCITRAL Arbitration Rules or any other arbitration rules selected by the disputing parties:
(i) Three months have elapsed from the date in which the award was rendered and no disputing party has commenced a proceeding to revise, set aside or annul the award; or
(ii) A court has dismissed or allowed an application to revise, set aside or annul the award and there is no further appeal.
9. A Contracting Party may not initiate proceedings in accordance with Section Two concerning the violation of the rights of an investor, unless the other Contracting Party fails to abide by or comply with a final award rendered in a dispute that such investor may have submitted pursuant to this Section. In this case, an arbitral tribunal established under Section Two of this Chapter may render, upon request of the Contracting Party whose investor was part in the dispute:Section Two concerning the violation of the rights of an investor, unless the other Contracting Party fails to abide by or comply with a final award rendered in a dispute that such investor may have submitted pursuant to this Section. In this case, an arbitral tribunal established under Section Two of this Chapter may render, upon request of the Contracting Party whose investor was part in the dispute:
(a) A statement that the failure to abide by or comply with the final award is inconsistent with the obligations set forth in this Agreement; and
(b) A recommendation that the other Contracting Party abide by or comply with the final award.
Article 21. Interim Measures of Protection
An arbitral tribunal may order an interim measure of protection to preserve the rights of a disputing party, or to ensure that the arbitral tribunal's jurisdiction is made fully effective, including an order to preserve evidence in the possession or control of a disputing party or to protect the arbitral tribunal's jurisdiction. An arbitral tribunal may not order attachment or enjoin the application of the measure alleged to constitute a breach referred to in Article 13. For purposes of this paragraph, an order includes a recommendation.
Section Two: Settlement of Disputes between the Contracting Parties
Article 22. Scope
This Section applies to the settlement of disputes between the Contracting Parties arising from the interpretation or application of the provisions of this Agreement. The alleged breach of a Contracting Party's obligation under Chapter II shall be settled as provided by Section One of this Chapter.
Article 23. Consultations and Negotiations
1. Either Contracting Party may request consultations on the interpretation or application of this Agreement.
2. If a dispute arises between the Contracting Parties on the interpretation or application of this Agreement, it shall, to the extent possible, be settled amicably through consultations and negotiation.
3. In the event the dispute is not settled through the means mentioned above within six months from the date such negotiations or consultations were requested in writing, any Contracting Party may submit the dispute to an arbitral tribunal established in accordance with this Section or, by agreement of the Contracting Parties, to any other international tribunal.
Article 24. Establishment of the Arbitral Tribunal
1. Arbitration proceedings shall initiate upon written notice delivered by one Contracting Party (the requesting Contracting Party) to the other Contracting Party (the respondent Contracting Party) through diplomatic channels. Such notice shall contain a statement setting forth the legal and factual grounds of the claim, a summary of the development and results of the consultations and negotiations pursuant to Article 23, the requesting Contracting Party's intention to initiate proceedings under this Section and the name of the arbitrator appointed by such requesting Contracting Party.Article 23, the requesting Contracting Party's intention to initiate proceedings under this Section and the name of the arbitrator appointed by such requesting Contracting Party.
2. Within 30 days after the delivery of such notice, the respondent Contracting Party shall notify to the requesting Contracting Party the name of its appointed arbitrator.
3. Within 30 days following the date in which the second arbitrator was appointed, the arbitrators appointed by each Contracting Party shall select by mutual agreement a third arbitrator who, on approval of the Contracting Parties, shall act as the presiding arbitrator.
4. If within the time limits provided for in paragraphs 2 and 3 above, the required appointments have not been made or the required approvals have not been given, either Contracting Party may invite the President of the International Court of Justice to appoint the arbitrator or arbitrators not yet appointed. If the President is a citizen or a permanent resident of either Contracting Party, or he or she is otherwise unable to act, the Vice-President shall be invited to make the referred appointment(s). If the Vice-President is a citizen or a permanent resident of either Contracting Party, or he or she is otherwise unable to act, the Member of the International Court of Justice next in seniority who is not a citizen nor a permanent resident of either Contracting Party shall be invited to make the necessary appointment(s).paragraphs 2 and 3 above, the required appointments have not been made or the required approvals have not been given, either Contracting Party may invite the President of the International Court of Justice to appoint the arbitrator or arbitrators not yet appointed. If the President is a citizen or a permanent resident of either Contracting Party, or he or she is otherwise unable to act, the Vice-President shall be invited to make the referred appointment(s). If the Vice-President is a citizen or a permanent resident of either Contracting Party, or he or she is otherwise unable to act, the Member of the International Court of Justice next in seniority who is not a citizen nor a permanent resident of either Contracting Party shall be invited to make the necessary appointment(s).
5. In case an arbitrator appointed as provided for in this Article resigns or becomes unable to act, a successor shall be appointed in the same manner as that prescribed for the appointment of the original arbitrator, and he or she shall have the same powers and duties that the original arbitrator had.
Article 25. Proceedings
1. Once convened by the presiding arbitrator, the arbitral tribunal shall determine the seat of arbitration and the date of initiation of the arbitral process.
2. The arbitral tribunal shall decide all questions relating to its competence and, subject to any agreement between the Contracting Parties, determine its own procedure, taking into account the PCA Optional Rules.PCA Optional Rules.
3. At any stage of the proceedings and before it issues any resolution, the arbitral tribunal may propose to the Contracting Parties that the dispute be settled amicably.
4. At all times, the arbitral tribunal shall afford a fair hearing to the Contracting Parties.
Article 26. Award
1. The arbitral tribunal shall reach its decision by majority vote. The award shall be issued in writing and shall contain the applicable factual and legal findings. A signed award shall be delivered to each Contracting Party.
2. The award shall be final and binding on the Contracting Parties.
Article 27. Applicable Law
A tribunal established under this Section shall decide the issues in dispute in accordance with this Agreement and with the applicable rules and principles of international law.
Article 28. Costs
Each Contracting Party shall bear the costs of its appointed arbitrator and of any legal representation in the proceedings. The costs of the presiding arbitrator and of other expenses associated with the conduct of the arbitration shall be borne equally by the Contracting Parties, unless the arbitral tribunal decides that a higher proportion of costs be borne by one of the Contracting Parties.
Chapter IV: Final Provisions
Article 29. Application of the Agreement
This Agreement applies to investments made before or after its entry into force, but not to claims arising out of events which occurred, or to claims which had been settled, prior to that date.
Article 30. Consultations
A Contracting Party may propose to the other Contracting Party to carry out consultations on any matter relating to this Agreement. These consultations shall be held at a place and at a time agreed by the Contracting Parties.
Article 31. Environmental Measures
The Contracting Parties recognize that it is inappropriate to encourage investment by relaxing domestic health, safety or environmental measures. If a Contracting Party considers that the other Contracting Party has offered such an encouragement, it may request consultations under Article 30 with the latter with a view to avoiding any such encouragement.
Article 32. Denial of Benefits
The Contracting Parties may decide jointly in consultation to deny the benefits of this Agreement to an enterprise of the other Contracting Party and to its investments, if a natural person or enterprise of a non-Contracting Party owns or controls such enterprise.
Article 33. Entry Into Force, Duration and Termination
1. The Contracting Parties shall notify each other in writing and through diplomatic channels the fulfilment of their constitutional requirements in relation to the approval and entry into force of this Agreement.
2. This Agreement shall enter into force 30 days after the date of the latter of the two notifications referred to in paragraph 1 above.paragraph 1 above.
3. This Agreement shall remain in force for a period of 10 years. Thereafter it shall continue in force until the expiration of 12 months from the date on which either Contracting Party shall have given written notice of termination to the other.
4. The provisions of this Agreement shall continue in effect with respect to investments made while the Agreement was in force for a period of 10 years after the date of termination.
5. This Agreement may be modified by mutual consent of the Contracting Parties, and the agreed modification shall come into effect pursuant to the procedures set forth in paragraphs 1 and 2 above.paragraphs 1 and 2 above.
Conclusion
FOR THE GOVERNMENT OF THE UNITED MEXICAN STATES
Alejandro Nemo Gómez Strozzi
Undersecretary of Standards, Foreign Investment and Trade Remedies
FOR THE GOVERNMENT OF THE REPUBLIC OF TRINIDAD AND TOBAGO
Kenneth Valley
Minister of Trade and Industry
Attachments
1. The notice of intent referred to in Article 12.2 shall be delivered:Article 12.2 shall be delivered:
In the case of Mexico, at the Directorate General for Foreign Investment of the Ministry of Economy; and
In the case of Trinidad and Tobago, at the Permanent Secretary of the Ministry of Foreign Affairs.
Any change in the above mentioned venues shall be duly notified by the relevant Contracting Party to the other Contracting Party. The disputing investor shall submit the written notice of intent referred to in Article 12.2 in Spanish or in English, depending on the Contracting Party against which the claim is made. The corresponding translation, made by an expert, shall be included in case such notice of intent is submitted in any language other than the aforementioned.
2. In order to facilitate the process of consultation, the investor shall provide along with the notice of intent, copy of the following documentation:
(a) Passport or any other official document of nationality, where the investor is a natural person, or the applicable document of incorporation or organization under the law of the non-disputing Contracting Party where the investor is an enterprise of such Contracting Party;
(b) Where an investor of a Contracting Party submits a claim to arbitration on behalf of an enterprise:
(i) The applicable document of incorporation or organization under the law of the disputing Contracting Party; and
(ii) Document evidencing that the disputing investor owns or controls the enterprise.
(c) Where applicable, power of attorney or the document whereby a person is duly authorized to act on behalf of the disputing investor.

Send a comment about this document
Report an error, missing information or a wrong category. The administrators review every comment.
Thank you for your comment
We will review it and reply to .
We will review it soon.